SAP PP Online Quiz


Following quiz provides Multiple Choice Questions (MCQs) related to SAP PP. You will have to read all the given answers and click over the correct answer. If you are not sure about the answer then you can check the answer using Show Answer button. You can use Next Quiz button to check new set of questions in the quiz.

Questions and Answers

Q 1 - In which of the Production type, produce materials changed with each lot and costs are calculated as per orders and lots?

A - Repetitive production

B - Discrete Production

C - Manufacturing Production

D - Material Requirement Planning

Answer : B

Explanation

Discrete production is known as industry where produce materials changed with each lot and costs are calculated as per orders and lots.

In Repetitive production, product is not changed for longer time period and production is done as total quantity and not in the form of individual lots.

Q 2 - In SAP PP, which of the following object is at the top in an Organization structure?

A - Plant

B - Company Code

C - Sales Organization

D - Storage Location

Answer : B

Explanation

In SAP PP module, organization structure defined the location of manufacturing plants and storage locations within the plant. At the top you have company and company code and then each company code contains different plant and storage locations.

Answer : A

Explanation

Key Features related to Routing −

To create routing it is mandate that you first define work center.

Multiple material can follow single routing group.

Routing is used for scheduling and costing of operation for raw and finished products.

Routing is used for calculation operation cost for finished product.

Q 4 - Which of the following Planning strategy is used to produce stock without Sales Order?

A - Make to Order

B - Make to Stock

C - Both of These

D - None of these

Answer : B

Q 5 - Which of the following doesn’t represent an issue Material Requirement Planning element?

A - Sales Order

B - PIR

C - Transfer Order

D - Production Order

Answer : D

Explanation

Issues include PIRs, Dependent Requirements, Order Reservations, Sales Orders, Issuing Stock Transfer Orders, etc. and receipts include Production Orders, Purchase Requisitions, Purchase Orders, Open Production Orders, Receiving Stock Transfer Order, Schedule lines, etc.

Q 6 - Which of the following Order type is used to define the material to be produced, plant location where production has to be done, date and time, quantity of goods required?

A - Production Order

B - Planned Order

C - Purchase Order

D - Sales Order

Answer : A

Explanation

A Production order is used to define the material to be produced, plant location where production has to be done, date and time of production, quantity of goods required. A Production Order also defines which components and sequence of operations are to be used and how the order costs are to be settled.

Q 7 - Simulative planning is performed only for long duration and it is not performed for short term and when there is no time restriction?

A - True

B - False

Answer : B

Q 8 - To perform Goods issue reversal, what is the movement type?

A - 261

B - 262

C - 263

D - 264

Answer : B

Q 9 - Which of the following report is used to collect information about hierarchy of work center of a shift?

A - Shift Transfer Report

B - Shift Report

C - Shift Work center Report

D - None of these

Answer : B

Answer : C

sap_pp_questions_answers.htm